As I mentioned previously, public transport actually works fairly well in Brisbane. So well in fact that they need additional trains to increase capacity, and so they spend $550 million on 44 new trains due to be in service by May.[pP]>dawload mu elite
However, it appears that the air conditioning units on the top of the carriages are 1cm too high. This means that they don't fit through a 4m stretch of tunnel between Central and Brunswick St stations - part of the network that pretty much every single route goes through.[pP]>dawload mu elite
So we have some nice new trains that cannot be used on the most popular routes where a capacity increase is most needed.[pP]>dawload mu elite
Oops...[pP]>dawload mu elite
I suppose it's better they found this issue in acceptance testing rather than during the first run of the train.[pP]>dawload mu elite